Location: Al Ruwais, United Arab Emirates
Client: Abu Dhabi Polymers Company Ltd. (Borouge)
Value: $25M – $75MTimeline: 2020-2022. 19 months
Scope: Engineering, Procurement, Construction, Pre-commissioning & Commissioning for CCCW Piping Upgradation In Borouge 3 Plant at Ruwais. Replacing the under-designed CCCW cracker supply piping with new piping. Laying down of pipings with various diameters with a single 108” (L 1.7 Km) parallel piping within available space. Total length 3 Km.
Unique Challenge: 108″ diameter pipeline erection in live plant. Complete shutdown tie-ins in 10 days
Client Satisfaction / Awards: Yes
C.A.T. Business Goals: Building new client’s trust
Sustainability: Sustainability requirements met
Local Resources: Pipes procured from UAE Manufacturer
Safety: 1.1M Man hours without incidents